Key Points

Most of a kitchen budget goes to 4 items: cabinets, countertops, removing walls, and changing the layout. Each one runs at least 5 figures.
360° Construction's quote leaves out appliances, but homeowners who want a full-kitchen number can ask for a $6,000 to $9,000 appliance ballpark.
After you sign with 360° Construction, the price moves for only 2 reasons: something unforeseen, like a missing section of sewer pipe behind a wall, or a change you ask for.

If you priced a kitchen a year or so ago, the number has changed. Here is where to start your budget, what moves it, and how to keep it from growing once work starts.

You’ll learn:

  • Where to start your kitchen budget
  • Which 4 parts of a kitchen move the price most
  • What our quote lists and what it leaves out
  • What can raise the price after you sign
  • What to do when a plan comes in over budget

Where Should My Kitchen Budget Start?

Our kitchen remodels average about $50,000 to $60,000 right now, closer to the $60,000 end. Then set aside a separate number for appliances, because our quote leaves them out.


What Moves a Kitchen Budget the Most?

Everything in a kitchen costs something, but 4 items carry the budget, and each one costs at least 5 figures:

  • Cabinets
  • Countertops
  • Removing walls
  • Changing the layout

Moving plumbing and electrical come next.

Long kitchen with a black range, wood cabinets, and a white range hood

Cabinets come first. We build ours, including glass-front inset doors like these, in our own shop. A box store cabinet comes in set sizes, but we build ours to fit your space.

A countertop choice can move the price a lot. On one kitchen, we priced quartz countertops, and the homeowners chose quartzite instead. Quartzite is a natural stone, and in our view a lot more durable. The countertop materials ended up costing twice what we had priced.

Many of the houses we work on are older, with a separate kitchen, dining room, and living room. Opening those rooms into one space usually means installing large beams to carry the load the walls held.

Layout changes come up on almost every kitchen remodel we do. Often, the layout doesn’t work for the homeowner, or there’s no island, so we build one and move the sink to it. That gives more countertop space where the sink used to be.


What Does a Kitchen Quote Include, and What Does It Leave Out?

Our quote lists each line of work with its price and says what that line includes and leaves out. The quote names the type of material, like the wood and the countertop, along with the grade of fixtures and quantities. Labor is built into the material lines.

See what a remodeling proposal should include.

Appliances are the big item we leave out. You pick your own, and we install them. Appliance orders get delayed, sometimes by 2-and-a-half to 3 months. Some homeowners change their pick just to get an appliance that arrives.

For your budget, treat appliances as a separate number. If you ask, we’ll put a $6,000 to $9,000 ballpark in the quote, and what you pick sets the final cost.

Before you sign any quote, ask what it says about permits. The City of Midland requires a residential building permit for remodeling.


How Do I Keep the Budget From Growing After We Start?

After you sign, 2 things can move a kitchen price:

  • Something unforeseen, like a missing section of sewer pipe behind a wall
  • A change you ask for

For the first, we go over every quote several times before you see it. If we see something that could be behind a wall, we tell you before you sign, along with roughly what it would add and the worst case.

For the second, if you change your mind, we tell you how it changes the time and cost. A change costs the least before construction, and that’s where our 3D design comes in.

3D design of a kitchen with white cabinets and a black range

We now design every project we take. You see your exact space in 3D, with a before and after, and you can move things before anything is built. Design takes more work up front, but it pays for itself, and it gives us a more accurate scope of work and material cost.

Say you’re looking at the rendering and decide you don’t like where the trash can pull-out sits. Before construction, moving it is a drag and a click. Once construction is done, moving that same pull-out can cost thousands of dollars.


What Happens if My Plan Comes in Over Budget?

Kitchen with a large white marble island, pendant lights, and wood cabinets

If the quote comes in over your number, you can scale back the scope. Start with the 4 big lines: cabinets, countertops, walls, and layout. A change there moves the price the most.

Before you cut something, picture the kitchen without it. On one Midland kitchen and bath job, the homeowners first took the island out of the plan because our price was over their budget. We told them we thought the island would complete the kitchen, and that leaving it off would mean a big empty space where it would go. They decided to keep the island.

This post can help you decide whether or not to install a kitchen island.


Ready to Plan Your Kitchen Budget With 360° Construction?

Tell us what you want to change in your kitchen and the number you have in mind, and we’ll write a quote with a price for each line. Fill out our contact form or give us a call.

For more on how we remodel kitchens, see our kitchen remodeling page.

Frequently Asked Questions

How much should I budget for a kitchen remodel with 360° Construction?

Our kitchen remodels average about $50,000 to $60,000 right now, with the average sitting closer to $60,000. Your number goes up or down mostly with the cabinets, the countertops, whether any walls come out, and whether the layout changes. Appliances are not in our quote, so add them on top, or ask us for a $6,000 to $9,000 appliance ballpark range.

How do I budget for appliances?

Give appliances their own line in your budget, apart from the remodel. You choose them, and we install them. Ask us, and we'll add a $6,000 to $9,000 ballpark to the quote, though the real cost follows what you choose.

What can change my kitchen quote after I sign?

Only 2 things change it: something unforeseen, like a missing section of sewer pipe behind a wall, or a change you ask for. If we spot something that might be hiding behind a wall, we point it out before you sign and give you the worst case. If you ask for a change, we give you the added time and cost.